PROJECT D1025
Commissioned May 2026

CASE STUDY | PULP & PAPER / WOOD PROCESSING

End-to-End Wood Chip Conveyor Automation for Continuous Pulp Production

A turnkey conveyor system delivered for Grasim Industries Ltd. — Harihar Plant, Karnataka, designed to automate wood chip flow from chipper discharge to digestor pre-bin and enable uninterrupted 24×7 pulp production.
0 TPH
Design Throughput Capacity
0

Conveyors Multi-Floor Plant

0 Cr
Total Project Value (Supply + I&C)
0 x7
Continuous Digester Operation

Project Overview

Client

Grasim Industries Ltd. (Aditya Birla Group)

Industry

Cellulosic Fibre Manufacturing (Viscose Staple Fibre / Rayon-Grade Dissolving Pulp)

India’s only rayon-grade pulp plant

Plant Location

Kumarapatnam – 581123, Karnataka, India

Project Ref.

D1025

Scope

Turnkey — Design, Supply, Fabrication, Erection & Commissioning

Contract Value

₹3.70 Cr (Supply) + ₹16.5 L (Instrumentation & Controls)

PO Date

20 August 2025

Commissioning

22 May 2026 (BC3–BC12) │ BC14 & BC15 no-load trial: 10 June 2026

System Scope

BC3 to BC15 — 13 conveyors for wood chip + 2 for pulp conveying

GIL Key Contacts

Panchakshari, Iranna, Anand (site) │ Pulkit Sharma, AGM — GIL Central Procurement Cell

The Challenge

Challenge 1 — Multi-Floor Plant Layout

  • Existing plant has 5+ floor levels; chips must travel both horizontally and vertically across existing civil structures.
  • Custom-engineered profile belts with bespoke steel structures were designed to fit within the existing civil footprint — each conveyor individually engineered.

Challenge 2 — Chip Quality Consistency for Dissolving Pulp

  • Dissolving pulp for VSF/lyocell requires uniform chip size and moisture; fines cause rejects in the digestor.
  • Enclosed belt conveyors with full weather covers and gentle transfer chutes were designed to minimise chip breakage and fines generation; belt speed controlled via VFD.

Challenge 3 — Continuous 24×7 Operation

  • Grasim runs the digestor continuously — any conveyor stoppage directly halts pulp production.
  • Redundant belt scrapers, auto belt-tracking, hot-vulcanised endless belts on critical conveyors (BC3/BC4), and robust drive frames with premium gearboxes were specified; 36-month warranty provided.

Challenge 4 — Site Constraints & Existing Civil

  • BC9 tail had only 150 mm gap from civil bed; BC15 floor level was 200 mm higher than original design.
  • On-site structural modifications executed by DEPL team: BC9 civil modification, BC15 legs cut 200 mm — all within commissioning schedule.

The Engineered Solution

System Architecture — Chip Flow

  • Chip receiving & screen feeding (BC3–BC5)
  • Chip segregation and inter-floor transfer between buildings (BC6–BC12)
  • Chip delivery to digestor pre-bin (BC14–BC15, digestor floor)
  • Pulp conveying and truck loading (separate line)

Key Automation Features

  • VFD-controlled drives — speed-matched to chipper output
  • Interlocked start/stop sequence (downstream first) — prevents material pile-up
  • Automatic belt tracking and alignment on all conveyors
  • Emergency pull-cord safety switches at all floor levels
  • Full enclosure covers — weather protection and dust containment
  • Redundant belt scrapers — keeps belts clean, reduces carryback

Results & Delivered Benefits

THROUGHPUT

  • Design capacity of 130 TPH matched to the Harihar plant’s wood chipper output, ensuring consistent chip supply to the digestor without buffer delays.
  • 10 of 13 conveyors (BC3–BC12) successfully load-trialled and commissioned on 22 May 2026 — on schedule.
  • BC14 and BC15 (digestor floor level) erection and no-load trials completed on 10 June 2026.
  • System operates continuously from chipper discharge to digestor pre-bin without manual intervention at any transfer point.

ROI & COMMERCIAL IMPACT

  • Replaced manual and bucket-elevator-based chip handling — eliminates 8–12 daily labourers from the chip yard operation.
  • Estimated annual labour saving: ₹30–40 Lakhs per year.
  • Chip spillage at transfer points reduced to near-zero vs. previous manual handling, which carried an estimated 2–3% wood loss per tonne (₹5,000/MT wood — a significant annual material saving).
  • Estimated payback on ₹4.20 Cr investment: 3–4 years on labour and wood loss savings alone, excluding productivity upside from uninterrupted digester operation.
  • Enables continuous 24×7 digester operation; eliminating chip supply stoppages directly protects pulp production throughput and plant revenue.

SAFETY IMPROVEMENTS

  • Manual chip handling at elevated floors (BC14/BC15 — digestor level) fully eliminated — major fall risk and prolonged dust exposure hazard removed.
  • Full enclosure covers on all conveyors provide dust containment; compliant with factory safety regulations.
  • Emergency pull-cord switches installed and operational at all floor levels.
  • Interlocked conveyor start sequence prevents unsafe or out-of-order machine activation.
  • Risk of loose chip accumulation and associated fire hazard significantly reduced through enclosed transfer and continuous operation design.

CLIENT RELATIONSHIP & STRATEGIC VALUE

  • GIL site team — Panchakshari, Iranna and Anand — formally acknowledged DEPL site engineer Dheeraj Gujar’s performance post-commissioning.
  • Project was won through a competitive tender process managed by GIL Central Procurement Cell (Pulkit Sharma, AGM) — demonstrating Dhanvanthri’s vendor qualification at Aditya Birla Group standards.
  • Relationship established with Aditya Birla Group’s global P&F procurement network — strategic foundation for future conveyor and automation orders across the group.

Marketing reference video capturing the system in full operation at the Harihar plant is available at: https://youtu.be/kONUbZ5Cq8k

Why This Matters For Project & Plant Leaders

For pulp, paper and agri-processing plants running continuous digestor or production cycles, the receiving and inter-floor conveying system is the most critical point of failure. A stoppage here does not just create a maintenance event — it halts an entire continuous process that may take hours to restart.

Dhanvanthri Engineers’ approach on this project — engineering each conveyor to the existing civil footprint, specifying redundant safety features, and commissioning within the client’s production schedule — demonstrates the value of a turnkey partner who understands the process, not just the machine.

Delivered Benefits At A Glance

Uninterrupted Production

Labour Cost Reduction

Safer Work Environment

Strategic Client Win

24×7 chip supply to digestor with zero manual intervention

₹30–40 L/year saving; 8–12 workers redeployed from chip yard

Elevated floor handling eliminated; dust and fire risk reduced

Aditya Birla Group vendor qualification — gateway to future orders